Thursday 11 April 2013

The news at ten.

This week has seen much activity at the unit; the stainless welders are doing a superb job and can seemingly make anything we ask them to, we've part-made a conditioning room with kingspan, the heat exchanger has been fully piped up and is in process of being stripped down and cleaned, we've done a full water run-through on all the pipework and pumps which was an almost complete success and we're painting the floor.

Plus we've picked up the first of our initial batch of plastic casks and very...  Erm... Turquoise they are too.

It all happens down in Tyla Garw!

The new cask filler
The very phallic-looking CIP sprayball.  Honestly, it is.

No comments:

Post a Comment